JEE Main 23 January 2026 Shift 1: Mathematics Question 12

Quadratic EquationsSingle correct option+4 / −1

A building construction work can be completed by two masons A and BB together in 22.522.5 days. Mason A alone can complete the construction work in 2424 days less than mason BB alone. Then mason A alone will complete the construction work in :

Show answer and solution

Correct answer: Option 3

Let A take tt days; BB then takes t+24t + 24 days. Their daily work rates add, so 1t+1(t+24)=122.5\frac{1}{t} + \frac{1}{(t + 24)} = \frac{1}{22.5} =245= \frac{2}{45}.

Cross-multiplication gives 45(2t+24)=2t(t+24)45(2t + 24) = 2t(t + 24), or t2 −21t−540=0{t}^{2}\ - 21t - 540 = 0. This factors as (t−36)(t+15)=0(t - 36)(t + 15) = 0.

Only the positive root is admissible. A takes 3636 days, option 33; BB takes 6060 days, and 136+160=122.5\frac{1}{36} + \frac{1}{60} = \frac{1}{22.5} checks the result.